The role of time and cost control in CPM, PERT, and EVA methods in construction projects: A meta-analysis study on evaluating project performance

(1) * E W P Ramdani Mail (Magister of Architecture, University of Merdeka Malang, Indonesia)
(2) P Tutuko Mail (Department of Architecture, University of Merdeka Malang, Indonesia)
(3) H Budiyanto Mail (Department of Architecture, University of Merdeka Malang, Indonesia)
(4) Susanto Susanto Mail (Department of Civil Engineering, University of Merdeka Malang, Indonesia)
*corresponding author

Abstract


Time and cost efficiency without reducing quality is something that construction service providers always want to achieve in the implementation of project completion. Project work will be limited by cost and time in completion. Methods of controlling time and costs can assist the Project Manager in evaluating project performance and taking actions needed to achieve project objectives. This study is about the comparison of research articles that have been published previously using Meta-Analysis Review which aims to compare three methods that are often used in controlling time and cost, namely CPM (Critical Path Method), PERT Method (Project Evaluation Review Technique), and EVA Method (Earned Value Analysis). The results obtained from the review of this article that each method of controlling costs and time has advantages and disadvantages following their respective characteristics, with that we can know differences of each method. The study found that experience from the Project Manager is needed to choose the right method for implementing project work.

   

DOI

https://doi.org/10.31763/aet.v1i1.668
      

Article metrics

10.31763/aet.v1i1.668 Abstract views : 1924 | PDF views : 732

   

Cite

   

Full Text

Download

References


[1] A. Mishakova, A. Vakhrushkina, V. Murgul, and T. Sazonova, “Project Control Based on a Mutual Application of Pert and Earned Value Management Methods,” Procedia Eng., vol. 165, pp. 1812– 1817, Jan. 2016, doi: 10.1016/J.PROENG.2016.11.927.

[2] A. Ridwan and R. Ajiono, “Pengendalian Biaya Dan Jadual Terpadu Pada Proyek Konstruksi,” UKaRsT, vol. 1, no. 1, p. 80, 2018, doi: 10.30737/ukarst.v1i1.84.

[3] E. Sonalitha, B. Nurdewanto, S. Ratih, N. R. Sari, A. B. Setiawan, and P. Tutuko, “Comparative Analysis of Tsukamoto and Mamdani Fuzzy Inference System on Market Matching to Determine the Number of Exports for MSMEs,” 2018 Electr. Power, Electron. Commun. Control. Informatics Semin. EECCIS 2018, pp. 440–445, Jul. 2018, doi: 10.1109/EECCIS.2018.8692989.

[4] M. Yu, X. Ding, H. Sun, K. Yu, and D. Zhao, “Role of fuzzy fractional differential equation in the construction of low carbon economy statistical evaluation system,” Alexandria Eng. J., vol. 59, no. 4, pp. 2765–2775, Aug. 2020, doi: 10.1016/J.AEJ.2020.05.031.

[5] J. (Junaidi) Junaidi, H. (Huibert) Tarore, G. Y. (Grace) Malingkas, and D. R. (D) Walangitan, “Pengendalian Waktu Dan Biaya Pada Tahap Pelaksanaan Proyek Dengan Menggunakan Metode Nilai Hasil (Studi Kasus : Proyek Lanjutan Pembangunan Gedung Pip2b Kota Manado),” J. Sipil Statik, vol. 1, no. 1, p. 131571, 2012, Accessed: Mar. 12, 2021. [Online]. Available: https://www.neliti.com/publications/131571.

[6] I. Widiasanti and Lenggogeni, Manajemen Konstruksi. 2013.

[7] E. R. (Ezekiel) Iwawo, J. (Jermias) Tjakra, and P. A. (Pingkan) Pratasis, “Penerapan Metode Cpm Pada Proyek Konstruksi (Studi Kasus Pembangunan Gedung Baru Kompleks Eben Haezar Manado),” J. Sipil Statik, vol. 4, no. 9, p. 139935, 2016, Accessed: Mar. 12, 2021. [Online]. Available: https://www.neliti.com/publications/139935/.

[8] J. S. (Juan) Simatupang, A. K. (A) Dundu, and M. (Mochtar) Sibi, “Pengaruh Percepatan Durasi Terhadap Waktu Pada Proyek Konstruksi (Studi Kasus : Pembangunan Persekolahan Eben Haezar Manado),” J. Sipil Statik, vol. 3, no. 5, p. 140219, 2015, Accessed: Mar. 12, 2021. [Online]. Available: https://www.neliti.com/publications/140219/.

[9] H. Olivieri et al., “Survey Comparing Critical Path Method, Last Planner System, and Location-Based Techniques,” J. Constr. Eng. Manag., vol. 145, no. 12, p. 04019077, Sep. 2019, doi: 10.1061/(ASCE)CO.1943-7862.0001644.

[10] A. Abdurrasyid, L. Luqman, A. Haris, and I. Indrianto, “Implementasi Metode PERT dan CPM pada Sistem Informasi Manajemen Proyek Pembangunan Kapal,” Khazanah Inform. J. Ilmu Komput. dan Inform., vol. 5, no. 1, pp. 28–36, Jun. 2019, doi: 10.23917/KHIF.V5I1.7066.

[11] F. H. Lermen, M. de F. Morais, C. Matos, R. Röder, and C. Röder, “Optimization of Times and Costs of Project of Horizontal Laminator Production Using Pert/Cpm Technical,” Indep. J. Manag. Prod., vol. 7, no. 3, pp. 833–853, 2016, doi: 10.14807/ijmp.v7i3.423.

[12] A. M. Aliyu, “Project Management using Critical Path Method (CPM): A Pragmatic Study,” Glob. J. Pure Appl. Sci., vol. 18, no. 3–4, pp. 197–206, Mar. 2013, doi: 10.4314/gjpas.v18i3-4.11.

[13] T. Hegazy and W. Menesi, “Critical Path Segments Scheduling Technique,” J. Constr. Eng. Manag., vol. 136, no. 10, pp. 1078–1085, Sep. 2010, doi: 10.1061/(ASCE)CO.1943-7862.0000212.

[14] H. Olivieri, O. Seppänen, and A. Denis Granja, “Improving workflow and resource usage in construction schedules through location-based management system (LBMS),” Constr. Manag. Econ., vol. 36, no. 2, pp. 109–124, Feb. 2018, doi: 10.1080/01446193.2017.1410561.

[15] M. A. Ammar, “LOB and CPM Integrated Method for Scheduling Repetitive Projects,” J. Constr. Eng. Manag., vol. 139, no. 1, pp. 44–50, Apr. 2012, doi: 10.1061/(ASCE)CO.1943-7862.0000569.

[16] A. W. (Apri) Laksana, H. S. (Heri) Prasetyo, M. A. (Mochammad) Wibowo, and A. (Arif) Hidayat,“Optimalisasi Waktu Dan Biaya Proyek Dengan Analisa Crash Program,” J. Karya Tek. Sipil S1 Undip, vol. 3, no. 3, pp. 747–759, 2014, Accessed: Mar. 12, 2021. [Online]. Available: https://www.neliti.com/publications/106820/.

[17] S. Zareei, “Project scheduling for constructing biogas plant using critical path method,” Renew. Sustain. Energy Rev., vol. 81, pp. 756–759, Jan. 2018, doi: 10.1016/J.RSER.2017.08.025.

[18] “Analisa Penerapan Manajemen Waktu Dan Biaya Pada Proyek Pembangunan Hotel BW Luxury Jambi.” Accessed Mar. 12, 2021. [Online]. Available: https://id.scribd.com/document/402353239/Analisa-Penerapan-Manajemen-Waktu-Dan-Biaya-PadaProyek-Pembangunan-Hotel-Bw-Luxury-Jambi.

[19] D. Trietsch and K. R. Baker, “PERT 21: Fitting PERT/CPM for use in the 21st century,” Int. J. Proj. Manag., vol. 30, no. 4, pp. 490–502, May 2012, doi: 10.1016/J.IJPROMAN.2011.09.004.

[20] M. Engwall, “PERT, Polaris, and the realities of project execution,” Int. J. Manag. Proj. Bus., vol. 5, no. 4, pp. 595–616, Sep. 2012, doi: 10.1108/17538371211268898/FULL/XML.

[21] D. Caesaron and A. Thio, “Analisa Penjadwalan Waktu dengan Metode Jalur Kritis dan PERT pada Proyek Pembangunan Ruko (Jl. Pasar Lama No. 20 Glodok),” JIEMS (Journal Ind. Eng. Manag. Syst., vol. 8, no. 2, Mar. 2017, doi: 10.30813/JIEMS.V8I2.124.

[22] S. A. NISAR, K. YAMAMOTO, and K. SUZUKI, “Resource-Dependent Critical Path Method for Identifying the Critical Path and the ‘Real Floats’ in Resource-Constrained Project Scheduling,” J. Japan Soc. Civ. Eng. Ser. F4 (Construction Manag., vol. 69, no. 4, p. I_97-I_107, 2013, doi: 10.2208/JSCEJCM.69.I_97.

[23] W. Lipke, “Earned Schedule Contribution to Project Management,” PM World J., vol. I, no. Ii, pp. 1– 19, 2003.

[24] E. Gardjito, “Pengendalian Jadwal Dan Anggaran Terpadu Dengan Metode Earned Value Analysis Pada Pekerjaan Konstruksi,” UKaRsT, vol. 1, no. 1, p. 19, 2018, doi: 10.30737/ukarst.v1i1.82.

[25] P. Ballesteros-Pérez, E. Sanz-Ablanedo, D. Mora-Melià, M. C. González-Cruz, J. L. Fuentes-Bargues, and E. Pellicer, “Earned Schedule min-max: Two new EVM metrics for monitoring and controlling projects,” Autom. Constr., vol. 103, pp. 279–290, Jul. 2019, doi: 10.1016/J.AUTCON.2019.03.016.

[26] P. A. de Andrade, A. Martens, and M. Vanhoucke, “Using real project schedule data to compare earned schedule and earned duration management project time forecasting capabilities,” Autom. Constr., vol. 99, pp. 68–78, Mar. 2019, doi: 10.1016/J.AUTCON.2018.11.030.

[27] Y. A. Messah, L. H. P. Lona, and D. A. T. Sina, “Pengendalian Waktu Dan Biaya Pekerjaan Konstruksi Sebagai Dampak Dari Perubahan Desain,” J. Tek. Sipil, vol. 2, no. 2, pp. 121–132, Sep. 2013, doi: 10.35508/JTS.2.2.121-132.

[28] A. Susanty, A. L. Pekerti, and D. P. Sari, “Analisis Kinerja Proyek Pembangunan Rumah Sakit Banyumanik Ii Dengan Menggunakan Earned Value Analysis (Eva) Dan Project Evaluation Review Technique (Pert).,” J@ti Undip J. Tek. Ind., vol. 11, no. 2, pp. 61–72, Jun. 2016, doi: 10.14710/JATI.11.2.61-72.

[29] B. Koke and R. C. Moehler, “Earned Green Value management for project management: A systematic review,” J. Clean. Prod., vol. 230, pp. 180–197, Sep. 2019, doi: 10.1016/J.JCLEPRO.2019.05.079.

[30] Y. A. Effendi and R. Sarno, “Non-linear optimization of critical path method,” Proceeding - 2017 3rd Int. Conf. Sci. Inf. Technol. Theory Appl. IT Educ. Ind. Soc. Big Data Era, ICSITech 2017, vol. 2018- January, pp. 90–96, Jul. 2017, doi: 10.1109/ICSITECH.2017.8257091.

[31] J. Hasil Penelitian dan Karya Ilmiah and A. Ilma, “Analisa Penjadwalan Proyek Menggunakan PDM dan Pert Serta Crash Project (Studi kasus: Pembangunan Gedung Main Power House PT. Adhi Karya),” J. Tek. Ind. J. Has. Penelit. dan Karya Ilm. dalam Bid. Tek. Ind., vol. 2, no. 1, pp. 31–43, Jun. 2016, doi: 10.24014/JTI.V2I1.5061.

[32] G. P. Arianie and N. B. Puspitasari, “Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi Dan Efektifitas Sumber Daya Perusahaan (Studi Kasus : Qiscus Pte Ltd),” J@ti Undip J. Tek. Ind., vol.12, no. 3, pp. 189–196, Sep. 2017, doi: 10.14710/JATI.12.3.189-196.

[33] D. Bryde, C. Unterhitzenberger, and R. Joby, “Conditions of success for earned value analysis in projects,” Int. J. Proj. Manag., vol. 36, no. 3, pp. 474–484, Apr. 2018, doi: 10.1016/J.IJPROMAN.2017.12.002.

[34] L. M. Naeni, S. Shadrokh, and A. Salehipour, “A fuzzy approach for the earned value management,” Int. J. Proj. Manag., vol. 29, no. 6, pp. 764–772, Aug. 2011, doi: 10.1016/J.IJPROMAN.2010.07.012.

[35] A. Czemplik, “Application of Earned Value Method to Progress Control of Construction Projects,” Procedia Eng., vol. 91, pp. 424–428, Jan. 2014, doi: 10.1016/J.PROENG.2014.12.087.

[36] J. Colin, A. Martens, M. Vanhoucke, and M. Wauters, “A multivariate approach for top-down project control using earned value management,” Decis. Support Syst., vol. 79, pp. 65–76, Nov. 2015, doi: 10.1016/J.DSS.2015.08.002.

[37] M. C. P. Sing, D. J. Edwards, H. J. X. Liu, and P. E. D. Love, “Forecasting Private-Sector Construction Works: VAR Model Using Economic Indicators,” J. Constr. Eng. Manag., vol. 141, no. 11, p. 04015037, Jun. 2015, doi: 10.1061/(ASCE)CO.1943-7862.0001016.

[38] A. De Marco and T. Narbaev, “Earned value-based performance monitoring of facility construction projects,” J. Facil. Manag., vol. 11, no. 1, pp. 69–80, Feb. 2013, doi: 10.1108/14725961311301475/FULL/XML.

[39] H. L. Chen, W. T. Chen, and Y. L. Lin, “Earned value project management: Improving the predictive power of planned value,” Int. J. Proj. Manag., vol. 34, no. 1, pp. 22–29, Jan. 2016, doi: 10.1016/J.IJPROMAN.2015.09.008.

[40] S. Babar, M. J. Thaheem, and B. Ayub, “Estimated cost at completion: integrating risk into earned value management,” J. Constr. Eng. Manag., vol. 143, no. 3, Mar. 2017, doi: 10.1061/(ASCE)CO.1943-7862.0001245.

[41] A. Baldwin and D. Bordoli, Handbook for Construction Planning and Scheduling. Wiley Blackwell, 2014.


Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 E W P Ramdani et al.

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.


Applied Engineering and Technology
ISSN: 2829-4998
Email: aet@ascee.org | andri.pranolo.id@ieee.org
Published by: Association for Scientic Computing Electronics and Engineering (ASCEE)
Organized by: Association for Scientic Computing Electronics and Engineering (ASCEE), Universitas Negeri Malang, Universitas Ahmad Dahlan

View My Stats AET
Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.